Recycling and end-of-life

This page answers one question: when a battery module leaves your site, who is legally responsible for it and where does it actually go?

Most owners meet this question for the first time at the first module failure, years after commissioning, when it is too late to have arranged anything. The obligations were set at the point of purchase; the practical chain has to be built before it is needed.

A note on scope. This page describes obligations and the current state of the reverse chain. Where we can act, we say so. Where the market has no answer yet, we say that too, because a service page that pretends otherwise is worth less than one that doesn’t.


1. Who is the producer — and it is probably not who you think

Under Regulation (EU) 2023/1542, a producer is the manufacturer, importer, distributor or distance seller who, on a professional basis, first makes a battery available on the market of a Member State. That entity carries extended producer responsibility (EPR).

Apply that to a containerised system bought from a Chinese manufacturer:

Situation Who carries EPR
There is an EU importer or buyer of record — the entity that places the system on the market That entity. In a B2B containerised sale this is usually the buyer, not the manufacturer
The non-EU manufacturer sells directly into a Member State, with no EU importer The manufacturer, which must then appoint an authorised representative for EPR in each Member State where it places batteries (Article 56(3))

The consequence is worth stating plainly: if you bought a containerised system from outside the EU, you may be the producer. Not the manufacturer whose name is on the container.

It is a question your supply contract can answer in an afternoon, and it is considerably cheaper to answer now than after a regulator asks.

One distinction that causes confusion: the EPR authorised representative (registration, reporting, collection, treatment, recycling) is a different appointment from the product-compliance authorised representative (technical documentation, communication with authorities). Having one does not give you the other.

Key dates

Date What applies
18 August 2025 EPR obligations and waste-battery management (Articles 54–63)
18 February 2026 Carbon footprint declaration for rechargeable industrial batteries
18 February 2027 Battery passport for industrial batteries above 2 kWh
18 August 2027 Supply chain due diligence (postponed from 2025 by Regulation (EU) 2025/1561)
18 August 2031 Recycled content minimums begin

2. Belgium: the 16 MWh line

Belgium runs producer responsibility by waste stream and by region — OVAM in Flanders, SPW in Wallonia, Bruxelles Environnement in Brussels. Bebat is the collective scheme for batteries and registers participants across all three regions.

For stationary storage, Bebat draws a line at 16 MWh:

Installation size Route
≤ 16 MWh Collective scheme: an environmental contribution calculated per kilogram, plus a EUR 60 annual flat-rate contribution
Above 16 MWh The collective route is not available. The producer must submit an individual plan with an accompanying financial guarantee to the regions

The 16 MWh is assessed by summing all modules on one site — the environmental-technical unit under an environmental permit, or the company site where there is none — and later expansions count towards it.

Which means a two-site portfolio of 25 MWh per site sits above the line on each site, and a site built at 12 MWh that is later expanded may cross it.

Separately, for batteries above 25 kg — industrial, EV, data centre — Bebat charges an administrative contribution that does not cover end-of-life costs. The producer must provide a financial guarantee under Article 58(7): a pledged account, an on-demand bank guarantee, or insurance.

Netherlands. Producers register and report annually to Rijkswaterstaat. Stichting OPEN is the collective organisation, having absorbed Stibat’s operating organisation on 1 January 2024. Collective arrangements exist for portable, LMT, SLI and EV batteries; for industrial batteries, no collective solution exists yet and the sector is building one.

Luxembourg. Ecobatterien ASBL is the approved collective scheme, overseen by the Administration de l’environnement. Producers join it or apply for individual approval.


3. Transport: the point where most plans stop

Battery modules in transport are dangerous goods, and the classification turns entirely on the condition of the module.

Condition Packing instruction Practical consequence
Sound — new or intact end-of-life P903 (UN 3480 / UN 3481), ADR Class 9 Routine dangerous goods freight
Damaged or defective, not liable to react dangerously P908 / LP904, Packing Group II quality, non-combustible cushioning Handled by carriers equipped for it; no special authority approval
Critically damaged — liable to rapidly disassemble, react dangerously, produce a flame, a dangerous evolution of heat, or a dangerous emission of toxic, corrosive or flammable gases under normal conditions of carriage P911 / LP906, Packing Group I performance The packaging performance must be verified by a test specified and approved by the competent authority, and a copy of the approval must travel with the consignment

Air transport of damaged or defective lithium cells is forbidden under IATA Special Provision A154. There is no exception worth planning around.

Which authority approves P911/LP906 packaging:

Every consignment must carry the marking “DAMAGED/DEFECTIVE LITHIUM-ION BATTERIES”, a transport document stating “Transport in accordance with special provision 376”, and — for P911/LP906 — a copy of the competent authority approval.


4. Storage: where the chain is genuinely broken

This is the part of the picture that no amount of contract drafting fixes.

A module removed from a container has to go somewhere before it reaches a processor. In practice that means storage, and storage of damaged lithium batteries is where the market currently has the least to offer.

The regulatory position:

And the practical position, which is harder:

Insurance appetite for lithium storage risk has tightened. The European Electronics Recyclers Association records that operators face rising premiums or find they cannot agree insurance terms at all — with knock-on effects where an operating permit itself imposes insurance conditions. Meanwhile the Belgian waste sector federation reported battery fires at Belgian recycling companies tripling over three years, from 20 to 60 incidents annually.

Those two facts together explain why compliant storage capacity for damaged modules is scarce in the Benelux: the constraint is not permits or warehouse space. It is that the risk is difficult to insure.


5. Where material can actually go

Party What it does Documented position on damaged units
Umicore (Hoboken, Belgium) Final recycler; states an annual capacity of 7,000 tonnes of lithium-ion batteries and production scrap Acceptance criteria for thermal-event, fire- or water-damaged units are not published. Confirm in writing before relying on it
Van Peperzeel (Lelystad, Netherlands) Collector and pre-processor; explicitly handles damaged and defective batteries; operates discharge equipment; stores under PGS 37-2; ships onward to specialist recyclers Publishes acceptance conditions
Reneos network (Bebat, Stibat, GRS, Cobat, Batteriretur) Cross-border collection; explicitly offers solutions for damaged, defective and end-of-life lithium-ion batteries, packaged and transported under ADR to approved or notified facilities Covered

One capacity fact worth knowing. The Benelux is strong on collection and pre-treatment and weak on final recovery. Dutch research body TNO noted in 2026 that an industrial-scale black mass refining facility requires roughly 10,000 tonnes of input per year, while the Netherlands collected around 430 tonnes of EV batteries in 2025. The national vehicle recycling organisation states plainly that there are no end-processors in the Netherlands — material is processed in Germany, Belgium or France.

Practically: your modules will cross a border, and the number of destinations is small.


After a module leaves the cabinet, on-site assessment against ADR SP 376 forks into three routes — sound end-of-life (P903), stable defective (P908/LP904) or critically damaged (P911/LP906) — with storage as the scarce, hard-to-insure step and final recovery capacity mostly outside the Benelux

Illustrative scenario

A Flemish owner operates two 25 MWh sites with equipment bought from Chinese manufacturers through a European entity. Three years in, a module fails and is removed under RMA.

Two questions arise that were never asked at procurement. First, who is the producer? The supply contract shows a European buyer of record — so producer responsibility sits with the owner’s own group, not with the manufacturer. Second, which Bebat route applies? Each site is above 16 MWh, so the collective scheme is not available; an individual plan with a financial guarantee is required.

Neither answer is a crisis. Both would have taken an afternoon to establish at contract stage, and both are more expensive to establish retrospectively — particularly the financial guarantee, which is a negotiation with a bank or an insurer rather than a form.

The removed module itself is assessed on site against SP 376. It shows no thermal event and is classified as stable defective, packed under P908, and routed to a collector that accepts damaged units. Had it shown signs of thermal stress, the packaging would have moved to P911 — requiring competent-authority-approved packaging, with the approval travelling with the consignment.

Illustrative scenario based on typical Benelux configurations — not a client reference.


What we do, and what we do not

We are honest about the boundary here because the market is young and over-claiming would be easy.

What we do:

What we do not do:


Frequently asked questions

Am I the producer, or is the manufacturer? If there is an EU importer or buyer of record — the entity that first placed the system on the market — that entity carries extended producer responsibility. In most B2B containerised sales that is the buyer. If a non-EU manufacturer sold to you directly with no EU importer, the manufacturer is the producer and must appoint an EPR authorised representative in your Member State. Your supply contract will tell you which case you are in.

What is the 16 MWh threshold and does it apply to me? In Belgium, ESS installations up to and including 16 MWh can use Bebat’s collective scheme. Above that, an individual plan with a financial guarantee is required with the regions. The threshold sums all modules on one site and later expansions count towards it.

What happens to a module that has had a thermal event? It falls into the critical category under ADR SP 376, requiring P911 or LP906 packaging with competent-authority-approved performance, and a copy of the approval travelling with the consignment. Air transport is forbidden. Not every processor accepts such units — this should be confirmed in writing before it is needed, not after.

How long can I keep a damaged module on site? There is no single published time limit we could locate for Flanders. VLAREMA sets registration, quality-assurance and transport conditions rather than a headline holding period. Your own environmental permit may impose one, and insurer conditions often do. Fire safety guidance recommends removing damaged units from storage and production areas immediately.

Does the EU Battery Regulation require a battery passport for my system? From 18 February 2027, for industrial batteries above 2 kWh. What that means in practice for a containerised system depends on how the system is classified and who the producer is.

Can you handle the whole end-of-life chain for us? We assess, document, and arrange the movement to a permitted party. We do not take title, do not operate a facility, and do not give legal advice. Where the market has no answer — and for critically damaged units in the Benelux it currently has very few — we will tell you that rather than promise around it.


Regulatory position stated as at August 2026, with sources. The Dutch storage decision described in section 4 is a draft in consultation and its thresholds may change. This page is not legal advice.

Talk to our team about end-of-life obligations for your assets — info@bess.re.

Repair or Replace? The 2026 EU Compliance & Local Delivery Guide

Repair or Replace? The 2026 EU Compliance & Local Delivery Guide

Repair economics, the compliance map, and local delivery capability — for Chinese BESS manufacturers entering Europe.

Download the whitepaper →